Tag: My-projects

WATER LOSS REDUCTION IN PLASTERBOARD MANUFACTURING – ENERGY COST REDUCTION AND ENVIRONMENTAL BENEFITS

The Lafarge manufacturing team takes the challenge to use less water In plasterboard production, water serves two important functions. While some water is required to set the plaster, the majority is to give enough fluidity to the plaster slurry as it is being formed.This… Continue Reading “WATER LOSS REDUCTION IN PLASTERBOARD MANUFACTURING – ENERGY COST REDUCTION AND ENVIRONMENTAL BENEFITS”

HEAT RECOVERY SYSTEM IN ALTONA PLANT

Installation of a new heat recovery system at the Altona plant has the potential of reducing CO2 emissions by 1,600 tonnes While Matraville plant is using a 50% mix of recycled water and town water in their manufacturing process, in Altona, Melbourne they are… Continue Reading “HEAT RECOVERY SYSTEM IN ALTONA PLANT”

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 9

CONCLUSION Justification of this type of product change was questioned mainly due to some failures to identify faulty product and prevent it from being released to the market, as well as number of changes that were not successful and excessive loss of product resulted.… Continue Reading “GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 9”

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 8

Everywhere in the world, SAFETY is our PRIORITY It is compulsory to wear Safety Glasses, Safety Helmet and Safety Boots in our plant at any time. Change from 1312RE to 1312FR without stopping Board-line requires involvement of several operatorson the Wet End – Forming… Continue Reading “GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 8”

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 7

Everywhere in the world QUALITY is our reference! Change from 1312RE to 1312FR without stopping Board-line is a very complex change and one with ahigh degree of risk of producing some product that is not within our quality standards and specifications.There are many variables… Continue Reading “GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 7”

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 6

Case Study No. 2Change on 16/01/2008 Chart below is presenting Dryer temperature profile during this change. Core Mix phase went smoothly and without any incidents or spillages. Only one board was rejected at the Wet End Transfer (3 m long) to avoid excessive gap… Continue Reading “GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 6”

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 5

Case Study No. 1Change on 03/11/2007 Core Mix phase during this particular change of product took less than 7 minutes to complete. Face paper was spliced at 12:43 – 55 seconds after selection of Clay and Vermiculite and start of Fibre Glass Cutter. That… Continue Reading “GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 5”

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 4

Dryer Temperature Profilesunder different conditions Dryer in Matraville plant is made of 2 zones and has 8 decks. Dryer Chain speed is calculated by dividing Board-line speed with 16 (each deck accommodates 2 boards) Ideal Dryer Chain speed for 1312RE board manufactured at 30… Continue Reading “GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – MK 4”

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – Mk 3

Good preparation, communication and cooperation between operators on the “wet” side of the Board-line is essential for success of the change. Some advanced planning and changes could prove to be the factor determining success or failure of the change.

GUIDE FOR PRODUCT CHANGE WITHOUT STOPPING BOARD-LINE 1312RE T0 1312FR – Mk 2

Board weight changes dramatically from 8.1 kg/m2 for 1312RE board to 10.5 kg/m2 for 1312FR board. This represents change of approximately 40 kg/min to the Stucco set point. It is important to know that heavier board is harder to dry. Increase in board weight during this product change is achieved through slowing down Board-line and adding Fly-ash and Vermiculite to the mix. Reduction to Stucco set point during this change must FOLLOW reduction in Board-line speed to make sure that board weight is as required or HIGHER.